“Riverside” Housing Development (Old Creamery Site)
Development consists of 10 Units comprising of eight houses and two apartments
- Development Location: Turagh, Cappamore, Co. Limerick
- Planning Permission Number: 19/872
- Local Authority: Limerick City and County Council
- Commencement date of development: Wednesday, 24th April, 2024
- Builders Name: Martins Construction Ltd.
- Designer Name: Healy Partners (Architects)
Riverside development update from Building Contractor
Dated 09/03/2026
- House 1-10
- Rainwater Goods – 95% Completed
- External Windows/Doors – Completed
- Internal Works – 95% Completed
- External Painting – 95% Completed
- Apartment Stairwell – Plaster boarding – In Progress
- Boundary Wall – 90% Completed
- Boundary Railings – Completed
- Footpaths – 95% Completed
- Kerbs – 90% Completed
- Attenuation Tank – Completed
- Surface & Foul Drainage – Completed to boundary
- Mains Water system – Completed to boundary
- Chimney – Completed
- Bollards – Completed
- House Railings – Completed
- Road Build Up – In Progress
- Street Lighting – In Progress
- Council Snags – 80% Completed
- Site Office & Storage – Removed from site
- River Park Railing/Gates – In Production
- ESB – Connection to commence on 18th March. Power due to be connected by first week in April
Top Project Risk
Irish Water – Connection Date Required
Two Week Look Ahead
Footpath kerbing to continue
Footpaths to continue
Tarmac prep to continue
Boundary Wall to continue
Apartment Stairwell Flooring to commence