Housing Developments


Riverside” Housing Development (Old Creamery Site)

Development consists of 10 Units comprising of eight houses and two apartments

  • Development Location: Turagh, Cappamore, Co. Limerick
  • Planning Permission Number: 19/872
  • Local Authority: Limerick City and County Council
  • Commencement date of development: Wednesday, 24th April, 2024
  • Builders Name: Martins Construction Ltd.
  • Designer Name:  Healy Partners (Architects)

Riverside development update from Building Contractor
Dated 13/04/2026

  • House 1-10 
    • Rainwater Goods – 95% Completed
    • External Windows/Doors – Completed
    • Internal Works – Completed
    • External Painting – 95% Completed
    • Apartment Stairwell – Completed
    • Boundary Wall – Completed
    • Boundary Railings – Completed
    • Footpaths – Completed
    • Kerbs – Completed
    • Attenuation Tank – Completed
    • Surface & Foul Drainage – Completed to boundary
    • Mains Water system – Completed to boundary
    • Chimney – Completed
    • Bollards – Completed
    • House Railings – Completed
    • Road Build Up – Completed
    • Street Lighting – Completed
    • Council Snags – Completed
    • Site Office & Storage – Removed from site
    • River Park Railing/Gates – Completed
    • Tarmac – Completed to sited entrance
    • Bin Stores – On site
    • ESB – Connection works commenced. Power due to be connected in April

Top Project Risk

Irish Water – Connection Date Required

Two Week Look Ahead

Paving to commence

Line marking to commence

Bin stores to be fitted

Landscaping to commence

Apartment Stairwell Flooring to commence